Off-plan handover delays in Dubai: what the DLD registry shows

We analysed the official Dubai Land Department registry: of 1,569 projects under construction, 412 (26%) are already past their planned completion date. Where it happens most and what it means for buyers.

Where the data comes from

The Dubai Land Department publishes a registry of all registered projects on Dubai's open data portal (data.dubai). For each project it lists the developer, completion percentage, planned start and end dates and the escrow bank. We used the export of 2 October 2026 and selected projects with the status active, not started or pending.

A passed date is not a failure yet

The completion date in the registry is the planned one. A developer can agree an extension with RERA, and the registry is sometimes updated with a delay. So a passed date is a reason to ask questions, not proof of a problem. Look at the completion percentage: a project at 90% with a passed date will almost certainly hand over soon; one at 10% will not.

Areas where timelines slip more often

Areas with many small developers — Arjan, JVC, Dubai Marina — have a higher share of projects past their date: many buildings there come from companies on their first or second project. Master communities of large developers (Emaar's Dubai Creek Harbour, Dubai Hills, Nakheel's Dubai Islands) keep to schedule noticeably better.

How to protect yourself

Before booking, check the project in the DLD registry: status, completion percentage and escrow account. Compare the promised handover date with the planned date in the registry. Look at the developer's record: how many projects it has delivered and how late. Find the delay-compensation clause in the sales agreement (SPA).

What to do if handover is delayed

Buyers' money sits in an escrow account and is released to the developer as construction progresses, so it does not disappear when a project is late. If a project is cancelled, Dubai law returns the funds to buyers through the escrow bank under RERA supervision. Keep all communication with the developer in writing and follow updates to the completion percentage.

AreaUnder constructionPast dateShareAvg completion
Arjan391949%36%
Dubai Marina14643%46%
Jumeirah Village Circle (JVC)1677042%28%
Business Bay531936%26%
Palm Jumeirah23835%34%
Downtown Dubai21733%27%
DAMAC Hills9333%25%
MBR City & Meydan431228%15%
Al Furjan491224%18%
Jumeirah Village Triangle (JVT)40922%19%
Dubai South1052221%13%
Dubai Hills Estate34618%34%
Dubai Islands1031515%5%
Dubai Creek Harbour1716%26%

Source: Dubai Land Department — Real Estate Projects (data.dubai), 2026-10-02

How PromptEstates helps

PromptEstates shows the DLD registry data for every project — completion percentage, planned handover date and escrow bank — next to the price and payment plan.

Frequently asked questions

What does 'past the planned date' mean in the DLD registry?

It is the planned completion date the developer gave at registration. If it is in the past and the project is still under construction, the timeline has moved or the registry is not yet updated — ask the developer.

Will I get my money back if a project is cancelled?

Yes: payments are held in an escrow account, and if RERA cancels the project the funds are returned to buyers through the bank.

How often is the data updated?

The Dubai Land Department updates the registry regularly; we use the export of 2 October 2026.

Sources: Dubai Land Department

Find your project first.

Describe the apartment or villa you want to buy in your own words — AI matches off-plan real estate projects in Dubai, Abu Dhabi and other emirates and shows the analytics: price per m², area trends and rental yield.

Read next

What is off-plan property in DubaiOff-plan means buying an apartment or villa directly from the developer while the project is still being built. Most new homes in Dubai are sold this way.Read The DLD fee when buying property in DubaiThe DLD fee is the registration fee charged by the Dubai Land Department. It is 4% of the property price and is paid when the sale is registered.Read UAE Golden Visa through propertyThe Golden Visa is a long-term UAE residence visa with no local sponsor. You can get it by owning property worth at least AED 2 million. Below are the current 2026 conditions and a step-by-step application guide.Read Payment plans for off-plan property in DubaiOff-plan property in Dubai is usually sold on a developer payment plan, typically interest-free. The schedule of instalments is called the payment plan.Read How to check a developer in DubaiWhen you buy a home that is still being built, you trust the developer with your money for years ahead. Here is what to check before you book.Read Off-plan vs ready property in DubaiYou can buy a home in Dubai from the developer before completion, or one that is already built. Each option has its own advantages.Read The costs of buying an apartment in DubaiThe advertised price is not the whole amount. Buying a home in Dubai comes with mandatory fees and recurring charges.Read Can foreigners buy property in Dubai?Yes. Foreign nationals can buy homes in Dubai with full ownership in designated districts known as freehold areas.Read Rental yield in Dubai: how to calculate itRental yield shows what share of a home’s price you earn each year by renting it out. Work it out before you buy.Read The 2-year investor visa through Dubai propertyIf you own a completed home in Dubai, it can be the basis for a 2-year UAE residence visa. In April 2026 the Dubai Land Department removed the AED 750,000 minimum property value for sole owners.Read Dubai: the emirate's history and where to buy propertyIn half a century a pearl-diving settlement on Dubai Creek became one of the world's main business and tourism hubs — and the region's busiest off-plan property market.Read Abu Dhabi: the capital's history and where to buy propertyThe largest and wealthiest emirate covers most of the country. Its market is calmer than Dubai's, and buyers favour Saadiyat, Yas and Al Reem islands.Read Sharjah: the UAE's cultural capital and where to buyDubai's neighbour offers more affordable homes, museums and more traditional rules. Many people live in Sharjah and work in Dubai.Read Ajman: the smallest emirate and where to buyA compact emirate half an hour from Dubai with some of the lowest prices for seaside homes in the UAE.Read Umm Al Quwain: the quiet emirate of lagoons and where to buyThe calmest and least populated emirate, with mangrove lagoons. The market is still forming, and large developers have arrived.Read Ras Al Khaimah: mountains, sea and where to buyThe northernmost emirate, with mountains and beaches, is seeing a surge of buyer interest thanks to the Wynn resort on Al Marjan Island.Read Fujairah: the Gulf of Oman emirate and where to buyThe only emirate that lies entirely on the east coast, by the Gulf of Oman — mountains, diving and resorts far from city bustle.Read Escrow accounts in Dubai: how off-plan buyers' money is protectedIn Dubai, payments for an apartment under construction do not go to the developer directly: they go into an escrow account at a bank and are released in stages as the building rises. Here is how it works and what to check.Read How to choose an off-plan property in Dubai: a 12-point checklistTwelve things to check before booking an apartment in a building under construction in Dubai. Save the list and run every project on your shortlist through it.Read How to buy off-plan property in Dubai: every step from booking to keysAn off-plan purchase is not one transaction but a chain of 10 steps spread over 2–4 years. Here is each of them: what you sign, what you pay, what to check and where buyers most often go wrong.Read How to buy resale property in Dubai: a step-by-step guideOn the secondary market you buy a finished home from its owner, and the deal takes weeks, not years. Here is every step — from choosing an agent to the new title deed — and every cost on top of the price.Read Freehold areas in Dubai and the UAE: where foreigners can own propertyA foreigner can own an apartment or villa in the UAE outright only in designated areas — freehold zones. Here are those areas in Dubai and the other emirates, and how to check a specific property.Read UAE retirement visa: how to move to Dubai after 55The UAE issues a dedicated residence visa for retirees: five years, no employer or sponsor, renewable. Here is who qualifies, which financial condition you need to meet and how to apply.Read UAE visa through financial investment: fund, business and bank depositThe Golden Visa can be obtained not only through property but also through financial investment — a deposit in an investment fund or capital in a UAE company. Here are the options, thresholds and documents, and how they differ from a regular bank deposit.Read UAE residency through investment: all the options comparedThe UAE has no single 'investor visa' — there are several programmes with different thresholds and conditions. We put them side by side: how much you need to invest, how long the visa lasts, whether off-plan counts and whether family can be included.Read Property revaluation for the Golden Visa: if you bought below AED 2 millionFor a Golden Visa through property, what counts is not the price you paid but the property's value in an official valuation on the date you apply. If your home has gone up and is now worth AED 2 million or more, a revaluation can open the way to the visa.Read UAE mortgages for foreigners: how much you can borrow and howForeigners can take a mortgage from a UAE bank — both residents and people living abroad. Here are the Central Bank limits, the down payment, income requirements, every fee and what is different for off-plan.Read Property taxes in the UAE: what an apartment owner paysThe UAE has no annual property tax, and individuals pay no tax on rental income or capital gains. But there are fees — one-off at purchase and regular ones for upkeep. Here are all of them, plus the one people often forget: taxes in the country where you are tax resident.Read

Updated:

1 of 4

Let’s match projects to your request

What are you buying for?